Pacers unveil Section 1 renovations of Fieldhouse of the Long run task

The Pacers, Fever and Bankers Life Fieldhouse unveiled Stage 1 renovations of the Fieldhouse of the Future challenge Thursday, which stays on schedule despite the onset of the COVID-19 pandemic in March 2020.

The project, which is divided into 3 phases around a few several years, began from the “bottom-up” with several of the renovations in Period 1 addressing “infrastructure, mechanical, electrical, plumbing,”said Mel Raines, executive vice president for Company Communications, Local community Engagement, and Facility Operations. 

The 25-year lease extension Pacers operator Herb Simon signed in 2019 established aside $295 million to up grade the Fieldhouse, and Section 1 was its premier undertaking, using 50% of the available resources, Raines stated. Bankers Life Fieldhouse added a bigger, center-hung scoreboard, new seating, sideline clubs and suites and renovated the Indiana Fever locker place, exercise session facility and apply courtroom.